Work is progressing well at our Elmsett site. Savolit boarding is now complete in preparation for lime plastering.
We are cutting the tenons and mortises in preparation for the soleplates to be installed across the whole building. These are a type of joint that have been used for hundreds of years to join two pieces of wood (or other material). The tenon part acts as a peg, whilst the mortise is the hole/slot in which the tenon is inserted. They create a very strong, stable joint. We are protecting the original wattle and daub panels whilst doing this.
We have begun structural work on a new project in Little Cornard. The first job is removing the party wall chimney from ground to first floor, then we will install Helifix rods to the mortar joints. This will stop any movement from occurring. Next we will be removing the load bearing wall on the stairs and installing an oak frame. We will keep you updated on our progress!